How a floor finish can fail: A case study

The screeding contract for the recent screeding project for the new sports hall and changing area at Uxbridge College was taken up by a screeding contractor on behalf of the main contractor. The screed used was FlexiDry F2/14 day dry. Sports Hall The screed was laid to perfection. But when moisture tests were carried out in...

How to Prepare the Floor Substrate for Levelling Screeds and Toppings

The key to the successful implementation of a bonded application is to achieve a good bond between the substrate and the applied bonding coat. Proper preparation is the most important factor for achieving a successful floor screeding installation. Whatever topping or levelling screed is used to achieve the definitive floor level, it will only...